All City of Ottawa Culvert Replacement Program required Goldie Mohr Ltd to apply our approved dewater plan / erosion and sediment control plan as per MOECC regulations 63/16. Specific tasks of the above mentioned project included placing granular as per D-029, install retained soil system walls, install geotextile, waterproofing membrane reinforcement and protection board, backfill culvert and retained soil system walls, remove temporary flow passage system, place new asphalt and apply pavement markings, excavate and install armour stone walls, excavate water channel and install multiple riffle section and deep pools and reinstate water flow.