2018 Bilberry Creek Offsetting Habitat
The City of Ottawa Bilberry Creek project is a modification for following instream restoration opportunities / fish habitat enhancement. The above mentioned project includes excavating for a pond that will have Rootwads, large woody debris, deciduous trees, coniferous trees, deciduous shrubs, floating aquatic plants and rooted aquatic plants.
2018 McLachlan Road McNab Braeside
McLachlan Road rehabilitation and reconstruction of approximately 3.3km on McLachlan Road and approximately 0.5km on McLeod Road in Township of McNab Braeside. The work also included ditch grading and the replacement of the existing roadway crossing culverts and driveway culverts. There are multiple sections in the roadway where the existing vertical curve was modified to improve the functionality and safety of the roadway. Existing road was pulverized, graded and resurfaced with a 50mm asphalt wear course.
2018 Ministry of Transportation of Ontario Projects
Hwy 60 Browns Creek Culvert replacement required Goldie Mohr Ltd to install temporary flow bypass system and divert water flow, dewater and excavate, remove existing 2450mm CSP culvert, place granular bedding, install precast cut-off walls on both ends of the culvert, install 2800mm x 2700mm precast box culvert.
2018 City of Ottawa Culverts
All City of Ottawa Culvert Replacement Program required Goldie Mohr Ltd to apply our approved dewater plan / erosion and sediment control plan as per MOECC regulations 63/16. Specific tasks of the above mentioned project included placing granular as per D-029, install retained soil system walls, install geotextile, waterproofing membrane reinforcement and protection board, backfill culvert and retained soil system walls, remove temporary flow passage system, place new asphalt and apply pavement markings, excavate and install armour stone walls, excavate water channel and install multiple riffle section and deep pools and reinstate water flow.
2018 Culvert Projects
Goldie Mohr Ltd completed various culvert replacements including 6 East Culverts project, CWWE project and west Ottawa project.
2018 City of Ottawa Rehabilitation of Petrie Island Culverts
Rehabilitation of Petrie Island Culverts consist of removing existing culverts, placing tremie concrete, Installing polymer laminated steel plates, placing granulars as per D-029, place distribution slab and fine grade.
2017 Bilberry Creek Slope Repair and Retention
Repair of the slope on the edge of Bilberry Creek that had eroded over time, including erosion control measures.
2017 Braeside Waste Disposal Site Clean Up
Clean up and grubbing of the Waste Site in Braeside (Renfrew County) for site expansion.
2017 Carp Road Snow Dump Facility
2017 Culvert Repairs and Replacement
Goldie Mohr had a big year of culverts in 2017, check out the gallery for just a few of our successful projects!
2013 Campbell Drive Culvert
Replace existing culverts and resurface existing road.
2013 Construction of Conley Road Bridge
Replace existing culvert, resurface existing road and landscaping.
2013 Berrigan Drive and Longfield Drive Roundabout
Intersection modifications. Transformed a 4 way intersection to a roundabout.
2012 Skyline Complex
Project involved roads & parking lot reconstruction and landscape upgrades for pedestrian safety and infrastructure sustainability.
2012 LCBO – Colonnade Drive
Site services, excavation & backfill, curbs and asphalt.
2012 Bonnechere Airport Environmental Decomm
Environmental Project.
2012 Skyline Landscape Project
Heavy Civil Construction.
2012 Walkley Armoury Parking Lot Repaving
Provided labour, material, and equipment necessary for the repaving of the parking lot at Walkley Armoury
2012 Access Lane LCBO
Heavy Civil Construction
2010 CFS Leitrim Tile Drain
Heavy Civil Construction.
2010 Cambridge Street Reconstruction
Road Construction.
2008 Articulated Bus Facility
Heavy Civil Construction.
2007 Best Buy – Kanata Centrum
Excavation and backfill.
2006 Chapman Mills Catholic Elementary School
Heavy Civil Construction.
Francis Properties – Dunrobin Road
Removals of existing footings, hoist columns and oil tank.
Provided excavation and backfill for new building.
University of Ottawa – Parking Lot R Reconstruction
Complete reconstruction of existing parking lot including curb and landscaping.
Provence Avenue Reconstruction
Install sewer, water, roads, curbs, sidewalks, etc.
2013 Construction of Southwest Transitway Tunnel Portal
Excavation, ventilation and fencing.
Hunt Club Noise Wall
Project involves construction of approximately 3.6km of new noise barrier along Hunt Club Road.
Flewellyn Road Bridge Renewal
Replace existing culvert, resurface existing road and landscaping
Lawrence Street and Stone School Road Culvert Replacements
Replace existing culverts, resurface existing road and landscaping.
French Catholic School Kanata Lakes – Ed. Brunet & Assoc.
Excavation and backfill.
Michaelle Jean Elementary School – Barrhaven
Excavation and backfill.
Walmart – Innes Road
Excavation and backfill.
Hockey Life – Kanata Centrum
Excavation and backfill.
Hockey Life – Kanata Centrum
Excavation and backfill.
Play-it-again Sports – Terry Fox Drive North
Excavation and backfill.
Play-it-again Sports – Terry Fox Drive North
Excavation and backfill.
West – Murphy, Herzberg, Donnelly Roads
Road Construction – small culverts.
Richmond Road Widening
Road Construction.
Osgoode Link Trail, Osgoode to Leitrim
Road Construction.
2010 Fallowfield Transitway @ Woodroffe
Road Construction.
Nicolls Island Road Rehabilitation (Barnsdale @ Cecil Mowat)
Road Construction.
Wilhaven Subdivision
Road Construction.
French Catholic School Kanata Lakes
Heavy Civil Construction.
DCC CFS Leitrim Parking Lot
Heavy Civil Construction.
MTO Kanata Parking Lot Reconstruction, Terry Fox Patrol Yard
Heavy Civil Construction
Trail Road Storm Water Management
Heavy Civil Construction.
Munster Pumping Station Lagoon Rehab
Heavy Civil Construction.
2005 Connaught Rile Range Safety Berm
Heavy Civil Construction
March Road Plaza Trinity – Tweedale Sewer & Water
Nicolls Island Road Rehabilitation
Environmental Project
Petrie Island Park Development
Environmental Project
Lebreton Flats – Contaminated Excn & Haulage
Environmental Project.
Russell Road Culvert Upgrade and Replacement
Replacement of the culvert on Russell Road, including ditch grading, and tie in with existing storm system.
Metcalfe Subdivision Storm Pond
Excavation and grading of a new storm retention pond to serve the new development in Metcalfe.
Woodvale Pentecostal Church Parking Lot
Grubbing, grading and excavation, including laying base granulars for the Woodvale Church parking lot expansion.
Kanata Trinity Plaza On-Site Works & Stormwater Management Pond
This project involved site servicing for multiple commercial buildings, excavation/creation of a stormwater management pond. Excavate and backfill for building foundations, construct the parking lot for the new plaza.
Siteworks & Roadway Modifications – Richmond Village Square
Install site services, including a storm water management pond and new turning lanes to provide access to the retail stores.
Kanata North Elementary School
Performed site grading, building excavation, backfilling and site services
Demolition/Deconstruction of 4 East End Properties
Lester Road Subdivision
Performed site grading.
Parking Lot Improvements
This project involved the complete parking lot reconstruction including the excavation, site servicing , aggregate subgrade, asphalt and landscaping.